Fishermen will be able to use a small portion of the St. George Island fishing pier beginning this weekend.
The
pier has been barricaded off for over a month while repair work is done to the
structure.
The
pier was damaged last June during Tropical Storm Debby when it was hit by a
barge leaving a 165 foot gap that makes it impossible for people to access much
of the pier.
A
company called The Gulf Group is currently replacing the missing section of
bridge with a 16 foot wide timber pier held up by concrete piles.
It is now
believed that work will be finished in mid-August so that the entire pier can
be reopened to the public.
The work
was supposed to be complete by June 30th, and under the current
contract the company will lose 300 dollars a day for every day past June 30th
the work is incomplete.