It looks like it will be mid to late August before the repair work on
the St. George Island fishing pier will be finished.
Engineers
with Prebble Rish said that it will take at least that long to finish the job –
not only is the company that was hired for the project far behind schedule, but
there are also some problems with the pilings that will require more work to
make sure the structure is stable.
The
pier, which is actually a section of the old St. George Island bridge, was damaged in June of 2012 during Tropical Storm Debby when
it was hit by a barge.
The
barge knocked out three sections of roadway, leaving a 165 foot gap that makes
it impossible for people to access much of the pier.
Last
October the county commission approved a repair plan to replace the missing
section of bridge with a 16 foot wide timber pier held up by concrete piles.
A
company called the Gulf Group was hired to do the repairs.
At this
point the company has removed the rubble from the bay bottom and has driven one
pile so there is still plenty more work to be done.
And on
Tuesday the county had to approve a change order for the project that will
allow three more piles to be added.
Engineers
said that change is necessary to insure that the pier is stable.
The
additional piles will add about 17 thousand dollars to the cost of the project,
bringing the total to over 573 thousand dollars.
The
county will get some of that money back – the Gulf group has to return 300
dollars every day after July 1st that the project is not complete.
The
work is being paid for through a fund set up to maintain the fishing pier and
the county is taking legal action against the owner of the barge that damaged
the pier.
http://www.oysterradio.com e-mail manager@oysterradio.com with comments http://live.oysterradio.com/
No comments:
Post a Comment